All 2020 competitive nine percent reservation applications are now available, all accompanying market studies for applications are available here. Please note the competitive nine round continues on track with original timelines with staff currently reviewing (remotely) all mandatory items. Further, we anticipate maintaining the schedule we shared in January and will follow the dates below:

  • 4/8/20 Mandatory item deficiency notifications;
  • 4/17/20 Mandatory item responses due to Virginia Housing;
  • 5/7/20 Preliminary rankings announced / Begin comment period;
  • 5/14/20 End of comment period/ begin rebuttal period;
  • 5/21/20 End of rebuttal period;
  • 5/29/20 Final rankings announced, which are subject to Board approval in June;
  • 6/18/20 Review final rankings with VHDA Board;
  • Early to mid-July, 2020 VHDA mails Reservation documents;
  • October 1, 2020 Allocation application deadline; and
  • November 13, 2020 Finalize Allocations.